Peljesac bridge was opened in July 2022. The access roads are expected to be finished by the end of 2022. The bridge connects Komarna on the Croatian mainland with Brijesta on the Peljesac peninsula. At the present, the project stays on schedule, and currently, construction works on the bridge are …
Read more » Peljesac Bridge
The excavation of the last tunnel on the access roads of the Pelješac Bridge has been completed The 1290-meter-long Supava Tunnel was successfully breakthrough at the beginning of November this year. The tunnel is part of the Ston bypass, part of the access road to the Peljesac Bridge, which is expected to open …
Read more » Supava Tunnel
The third tunnel breakthrough in the Peljesac bridge project, the Polakovica tunnel, near Ston town, is completed in July 2021. The Greek company Avax successfully completed the excavation of the 1242 meters long Polakovica tunnel. The tunnel is part of the 4th phase of the Ston bypass and, together with the Ston bridge and the Supava …
Read more » Polakovica Tunnel
I was going throught some old press cuttings, looking for something completely unrelated, and found some old articles from local press with lot of info about future Peljesac Bridge. So, below is compillation of some facts and figures about this project:
Read more » Peljesac Bridge Map and Facts
Works began on Kamenice Tunnel @ Peljesac Bridge The works began on the excavation of the Kamenice tunnel. With a length of 499 meters, this is the shortest tunnel of the project and the second tunnel on the routes of access roads to the Peljesac Bridge. The previously excavated tunnel …
Read more » Kamenice tunnel
The works on the Peljesac Bridge are nearing completion. All works should be completed by the end of the month, followed by a technical inspection and the issuance of a use permit. Hrvatske Ceste says that a fence for wind protection is being erected on both sides of the bridge and a protective, …
Read more » Peljesac Bridge works close to completion
Boring of the tunnel on the Peljesac Bridge project begins In April 2020 workers of the Strabag company began boring the main tube of the 2,467-metre-long Debeli Brijeg tunnel, which is part of the second section of an access road to the Peljesac Bridge. The section is 12.1 km long and Strabag …
Read more » Debeli Brijeg Tunnel
According to Javno.hr, the director of the Croatian Construction Institute (IGH), Jure Radic said following info on the Croatian television show Nedjeljom u Dva, where one of the discussion topics were Peljesac Bridge : As far as building the bridge to Peljesac, Radic stresses that the strong southerly winds represent …
Read more » The latest news about Peljesac Bridge project
Some good and reassuring news are coming from Croatian media regards future of Peljesac Bridge, the important infrastructure object that was supposed to be built to connect the Croatian Mainland and Peljesac Peninsula. It has been reported that Bozidar Kalmeta, the Croatian Sea, Transport and Infrastructure Minister said in Zadar …
Read more » Peljesac Bridge will not be scrapped
A study to evaluate the effects of construction of Peljesac Bridge in the context of economic, transport and demographic changes of Peljesac Peninsula , Korcula , Mljet and its surrounding area, has been presented today at Hotel Villa Argentina in Dubrovnik, Croatia. According to the projections on which the study …